Delivery of oversized cargo for Baltic Chemical Complex



ABOUT THE PROJECT: 

  • Duration: June 6 – June 12, 2024
  • Route: Ust-Luga Port — Baltic Chemical Complex terminal
  • Task: transportation of an oversized (OOG) cargo to the Luga River for the Baltic Chemical Complex

PROJECT EXECUTION: 

  • The towing was completed in a short time, which has confirmed the effectiveness in handling the entire project
  • The main difficulty was the OOG cargo, which significantly limited visibility
  • To carry out this project the AHTS Wenna bridge was raised to create the necessary conditions for safe passage along a difficult route
  • The project was completed without the deployment of an auxiliary tugboat. The AHTS Wenna was pushed along the entire route, which required high concentration and skillful maneuvering
  • The route included a difficult section at the entrance to the Luga River, which is known for its narrowness and shallow water. Despite these conditions, the captain of the AHTS Wenna demonstrated a high level of professionalism, ensuring a safe and successful passage.
  • Upon arrival and mooring to the pier, the huge cargo was unloaded using the rolling-off method. This was also a difficult task, given the size of the cargo, but the operation was completed successfully.

ФЛОТ ПРОЕКТА: 

 

AHTS Wenna

Barge MORVENNA 3001