TASK:

  • Towing of 8 blocks SME-13 of the ice-resistant fixed platform LSPA from Astrakhan to Kaliningrad;

REALIZATION:

  • The blocks to be transported were not maneuverable. There were difficulties with the roll of the blocks. They were solved quickly and smoothly by the company representatives. All 8 blocks were delivered in perfect condition;
  • Towing was carried out in 2 tugs on the river and 1 tug per pair of blocks at sea. This made it possible to competently manage the construction and to deliver the blocks to Kaliningrad on time according to the contract.

PROJECT JUDGEMENT: