Transportation of hydroisodeparaffinization reactor



Project Summary: 

  • Duration: October 15 – November 24, 2024
  • Route: Novorossiysk – Ust-Donetsky
  • Cargo: hydroisodeparaffinization reactor 254 tn, (dimensions: 24.93 x 5.88 x 5.83 m)
  • Project fleet: tugs Muson and Hero Ivan Sivko, RORO pontoon Silver-3003.

PROJECT IMPLEMENTATION:

Mobilization of barge-tugboat train from Astrakhan to Ust-Donetsky in 7 days (October 15-22).

Installation of support bollards on the barge “Silver-3003” in Ust-Donetsky.

Obtaining permission for the Kerch Bridge passage during October 28 – November 1.

Provided power supply to the barge pumps during ballasting by means of a tugboat in order not to connect to shore power.

Direct cargo transshipment in Novorossiysk from the crane ship to the barge Silver-3003. 

The process of oversized transportation always requires careful preparation and planning: from obtaining permits in advance to organizing timely delivery of ramps to loading and back.

 

 

IMPORTANT: as the transshipment was carried out from the crane ship to the barge, the UBS arrived at the loading port well in advance to avoid the crane ship downtime.

 

The customer sent a letter of thanks for the successful transportation of the responsible cargo!