Transportation of blocks and components on the Simmar Sun barge



ABOUT THE PROJECT: 

  • Port of loading: Constanta, Bautino;
  • Start of loading: 06/01/2022;
  • Discharge port: Bautino, Kazakhstan;
  • Unloading end: 07/07/2022;
  • Project cargo: 3 blocks and accessories. The overall size of each block (LSHV 1230 * 794.5 * 1017), the total weight of the entire load is 771 542.4;
  • The actual transportation/movement of the tug-barge from the port of loading to the port of unloading took from 07.06 to 01.07 = 24 days;
  • Year – 2022;

PROJECT VESSELS: 

Transportation of blocks and components on the Simmar Sun barge
Transportation of blocks and components on the Simmar Sun barge

PROJECT ACHIEVEMENTS & SOLUTIONS:

  • In June 2022 loading in Constanta, Romania. The loading and exit of the BBS was carried out without delay.
  • Features of transportation: high-rise clearance.
  • The permitted limit on GDP is 14 m. The barge’s surface clearance + cargo height = 13.9 meters.
  • When unloading, no comments, the Customer appreciated the efficiency of transportation.