General cargo, parts and equipment of crawler cranes transportation to the Bay Sever



ABOUT THE PROJECT: 

  • Start of mobilization of the barge MORWENNA-3602 from Astrakhan: 13.07.2022;
  • End of mobilization and arrival in Arkhangelsk: 19.08.2022;
  • End of loading and start of the voyage from Arkhangelsk to Sever Bay: 25.08.22;
  • Arrival at the destination Bay Sever 03.09.22;
  • Year – 2022;

PROJECT VESSELS: 

Fleet Morwenna 3603
{:ru}Перевозка трубошпунта в Бухту Север{:}{:en}Mobilization of barge MORVENNA-3604 Bay Sever{:}

PROJECT ACHIEVEMENTS & SOLUTIONS:

  • Cargo on barge – general cargo, parts and equipment of crawler cranes.
  • We expected the end of navigation until 10/20/2022, but the weather conditions allowed us to perform a few more shunting operations.
  • At the moment, Sever Bay is only developing, construction of safe berths is underway, in connection with which the captains had to resolve issues of unloading with operators locally, which gave tremendous experience in this region.