Mobilization of barge MORVENNA-3604 Bay Sever



[/vc_column_text][/vc_column][/vc_row]

ABOUT THE PROJECT: 

  • Start of mobilization of barge MORVENNA-3604 from Astrakhan: 14.07.2022;
  • Arrival for loading of pipe sheet piling in Arkhangelsk: 09.16.2022;
  • Arrival at the destination Bay Sever 18.10.22;
  • Year – 2022;

PROJECT VESSELS: 

Fleet Morwenna 3603
Mobilization of barge MORVENNA-3604 Bay Sever

PROJECT ACHIEVEMENTS & SOLUTIONS:

  • The peculiarity of the project was to mobilize barges through Scandinavia. Due to sanctions, entry to foreign ports has been blocked for ships flying the Russian flag since March 2022, but bunkering of ships flying the Russian flag on the route from all reliable bunker fuel suppliers has become impossible before the planned departure.
  • But we found a way out: we built a mobilization route from St. Petersburg to Arkhangelsk with a change of 3 tugboats! As a result, the prem-transfer of the barge between 5 tugs and MV-3604 in Sever Bay!
  • SC Morwenna is ready to participate in the development of the north and offers to fix the available fleet in the village of Murmansk and in the village of Arkhangelsk!