Transportation of barges with vehicles



ABOUT THE PROJECT: 

  • Period: July-October, 2024
  • Route: Arkhangelsk – Dickson settlement, uch.2, Yenisei terminal – Arkhangelsk
  • Tugboat MB-1216 
  • Pontoons: TMI-5 and DAMEN RIVERSTAR 3
  • Cargo: wagons, trucks
MB-1216
MB-1216 1

PROJECT ACHIEVEMENTS & SOLUTIONS:

  • Transportation via the NSR (Northern Sea Route):
  • Loading in the port of Arkhangelsk;
  • Discharging in the port of Tochino, Yenisei.
  • Cargo handling operations (stevedoring) are the Customer’s responsibility.

Call at the port of Dikson, area 2, “Yenisei” terminal, Taimyr Peninsula, for:

  • Handover of the pontoon “TMI 5”;
  • Receipt of the barge “DRS 3” from the temporary mooring facility (hereinafter referred to as TMF).

Within 60 days, 2 voyages were completed, and transportation proceeded as planned.