Transportation of barges with vehicles



ABOUT THE PROJECT: 

  • Period: July-October, 2024
  • Route: Arkhangelsk – Dickson settlement, uch.2, Yenisei terminal – Arkhangelsk
  • Tugboat MB-1216 
  • Pontoons: TMI-5 and DAMEN RIVERSTAR 3
  • Cargo: wagons, trucks
MB-1216
MB-1216 1

PROJECT ACHIEVEMENTS & SOLUTIONS:

  • Transportation via the NSR (Northern Sea Route):
    • Loading in the port of Arkhangelsk;
    • Discharging in the port of Tochino, Yenisei.
    • Cargo handling operations (stevedoring) are the Customer’s responsibility.

    Call at the port of Dikson, area 2, “Yenisei” terminal, Taimyr Peninsula, for:

    • Handover of the pontoon “TMI 5”;
    • Receipt of the barge “DRS 3” from the temporary mooring facility (hereinafter referred to as TMF).

    Within 60 days, 2 voyages were completed, and transportation proceeded as planned.

     

For reference: The El-Dabaa NPP is the first nuclear power plant in Egypt. The project is being implemented by Rosatom on the northern coast of the country, 3.5 km from the Mediterranean Sea.